This page provides residents and local stakeholders with information about the construction work currently being carried out at our Victoria Deep Water Terminal site at 231 Tunnel Avenue, North Greenwich, SE10 0QE.

This critical work will ensure the wharf continues to function as an important tidal flood defence. It will reinforce the structure and minimise flood risk to the site and surrounding area, to comply with requirements established with the Environment Agency and the London Borough of Greenwich.

Below you will find the latest schedule for fender pile installation at the site. Piling work generates temporary noise and we appreciate your patience. All times are subject to change due to tidal conditions so please check back regularly for updates.

Fender pile installation schedule

Each pile installation is expected to take approximately one to two hours to complete and planned dates are as follows:

PilePrimary date and timeContingency date and time
P9 Fender piles14th July 07:30hrs – 09:30hrs15th July 08:30hrs – 10:30hrs
P3 Fender pile to complete15th July 08:30hrs – 10:30hrs16th July 09:30hrs – 11:30hrs
Remove 5 No existing piles (vibro only)16th July 09:30hrs – 11:30hrs20th July 12:00hrs – 14:00hrs
Bearing piles20th July 08:00hrs to 17:00hrs onwardsWill not be every day but could be for a full day
20th July to 14th August

Please note all works are carried out using a vibratory hammer to reduce noise and vibration where practicable. Working hours are governed by tidal conditions and all activity takes place within permitted daytime hours.

If you have any questions or concerns, please contact us at: communications@uk.heidelbergmaterials.com